Ridge Road Extension

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14

Project Details

Work Type

New Roadway Construction

Phase

Design and Permitting

Project Limits

Phase 1: Moon Lake Suncoast Pkwy w / interchange

Phase 2: Suncoast Parkway to US 41

Length

Phase 1: 22,200 feet / 4.2 miles

Phase 2: 18,181 feet / 3.4 miles

Budgeted Prior Years

$19,500,868

Total Expenditure to 3/7/2018

$16,564,487

Land Acquisition (Fiscal Year)

2018

Land Acquisition Cost

$2,600,000

Design of Interchange

$1,000,000*

Construction (Fiscal Year)

2018

Construction

Cost

Phase 1: $67,869,800

Phase 2: Not Funded

Total Project County Funding

$89,970,668

*Note, this sum is to be reimbursed by FTE for the design of the Suncoast Parkway Interchange.

Project Location

Phase 1 Project Area

Phase 1 Project Area

Phase 2 Project Area

Phase 2 Project Area

Click Pictures to see larger image. 

Contact Us

Sam Beneck
Project Manager

Pasco County Project Management

P (727) 847-2411 x1614


Fact Sheet
Adjacent Lands & Ownership
Landscape Button
Alternatives Analysis
Flow Chart
Wayside Renderings & Interpretive Signs