Wesbridge & Chapel Chase

Reclaimed Water Coming Soon to Wesbridge and Chapel Chase

Project updates will be posted to this webpage.

Update 3/31/21: The project is 95 percent complete. The contractor completed the installation of the 12-inch Polyvinyl Chloride (PVC) reclaimed water pipeline and will perform the Chapel Chase community connection in April.

Update 2/26/21: The project is 78 percent complete. The contractor began with installation of the Polyvinyl Chloride (PVC) pipe in February and will continue through March. The contractor also completed the installation of the 14-inch High Density Polyethylene (HDPE) reclaimed water pipeline.

Update 1/28/21: The project is at a 20 percent completion status, as the contractor began with installation of the 14-inch High Density Polyethylene (HDPE) reclaimed water pipeline. The contractor will continue with the installation of the HDPE pipeline and will start the installation of the Polyvinyl Chloride (PVC) pipe in February.

Update 12/29/20:  Pasco County issued a Notice to Proceed to the contractor on November 19, 2020. The contractor, Amici Engineering Contractor, will mobilize to the jobsite the first week of January 2021.

  • Contractor: Amici Engineering Contractor
  • Notice to Proceed: November 19, 2020
  • Project Duration: 210 Calendar Days
Picture of a map showing Boyette Rd. as noted in the text for the Wesbridge and ChapelChase project.

Update 11/30/20: The Pasco County Utilities (PCU) Engineering & Contract Management Department will soon bring reclaimed irrigation water to the Wesbridge and Chapel Chase communities in Wesley Chapel.  Construction on the much-anticipated projects is estimated to take six months.  Most work will occur outside the developments along Boyette Road, with no anticipated impact to local traffic.

Both communities have irrigation systems that are being fed by drinking water, with usage charged at current potable water rates.  The new systems will provide lower-cost, reclaimed irrigation water to the communities while helping conserve drinking water.  Bills will automatically reflect the new water source with no action required by residents.

“Wesbridge and Chapel Chase were originally built with separate potable and irrigation pipe networks,” said Utilities Engineering Director Charles J. Cullen.  “This design supports a smooth transition to cost-saving reclaimed irrigation and enhances our long-term conservation efforts as we keep pace with growth.”

Residents should anticipate an approximate 8-hour temporary outage of irrigation service when the final connection is made.  To minimize impacts, this work will be scheduled outside of normal watering hours. Disconnection and reconnection will not affect drinking water services inside the home at any time

View Media Release "Reclaimed Water Coming to Three Pasco Communities in 2021"